ONGOING CONSTRUCTION ACTIVITIES

Sunday, October 1 through Friday, October 6, 2023

Performing concrete, signal work and paving along West Dixie Highway and along NE 125 Street

  • Continuing work at the Five Points Park
  • Signalization work on West Dixie Highway and NE 125 Street; and along NE 123 Street and West Dixie Highway
  • Installing sidewalk throughout the project
  • Installing lighting along NE 125 Street and NE 7 Avenue
  • Directional boring along NE 125 Street and NE 6 Court NE 7 Avenue
  • Paving along NE 125 Street and West Dixie Highway
  • Installing traffic signs throughout the corridor

Lane Closures

  • One lane will be closed daily between 9 a.m. and 3:30 p.m.
  • Pedestrian access will be maintained during sidewalk work.
  • Please use caution and follow posted signs for the new traffic changes along West Dixie Highway, along NE 7 Avenue and on NE 124 Street

PLEASE NOTE THAT THIS SCHEDULE MAY CHANGE DUE TO WEATHER OR UNEXPECTED CONDITIONS.